|
The Pacific Connector Gas Pipeline project crosses a number of fish bearing
streams and areas which may be problematic for conventional pipeline construction.
To potentially avoid impacts to these sensitive areas, the HDD construction
methodology is being reviewed for feasibility.
The use of the HDD methodology at these locations will be determined
in consultation with a number of federal and state agencies including
the U.S. Army Corps of Engineers, National Marine Fisheries Service, U.S.
Fish and Wildlife Service, Oregon Department of Ecology, Oregon Department
of Fish and Wildlife, and Oregon Department of Natural Resources.
What is a Horizontal Directional Drill?
The HDD construction method can be used to install pipelines beneath
areas where conventional open trench or other construction techniques
may cause undesirable surface disturbance.
The HDD method tunnels beneath surface obstacles and then pulls the pipeline
back through the underground tunnel, leaving the surface undisturbed.
The tunnels are typically drilled to depths ranging from 25 to 100 feet
below surface obstacles, depending upon the location, pipe characteristics,
and subsurface conditions.
The HDD installation involves four main steps:
- Pre-Site Planning
Extensive pre-site planning is required to determine if the HDD method
is technically and geologically feasible. A topographic survey is performed
along the proposed drill site to ensure adequate surface area is available
to conduct the drilling process. In addition, a geotechnical investigation
is conducted at each drill site to determine the subsurface conditions.
Using the data from the geotechnical investigation and topographic survey,
a specific drill path is determined.
- Drilling the Pilot Hole
Once the entry location, exit location and trajectory have been determined,
the next step is the drilling of a pilot hole. The drill rig is set
up at the entry location.
When the drill rig is in place, drilling of a pilot hole begins.
At all stages along the drilling path, the operator receives information
regarding the position, depth, and orientation of the drilling tool,
allowing navigation of the drill head along the designed drill path
to the exit point.
- Hole Opening Process
Upon completion of the pilot hole, the hole opening or reaming process
begins. This process consists of progressively enlarging the pilot hole
to a diameter that will allow successful pullback of the prefabricated
pipe string.
- Pipe String Pullback
A pipe string consists of short sections (approximately 40 feet) of
steel pipe which are welded together to form a continuous string of
pipe for insertion into the drilled hole. The pipe string is slightly
longer than the length of the drilled hole. The pipe string is coated
with a layer of corrosion and abrasion resistant protective coatings
and hydrostatically pressure tested to insure its integrity. The pipe
string is then placed on rollers and cradles to assist with movement
during pullback. Next, the pipe string is pulled over the rollers and
down into the drilled hole. The pullback continues until the entire
length of the pipe string has been pulled into the drilled hole.
- Environmental and Safety Measures
Pacific Connector will employ specialists at each HDD installation with
a proven record of successful completion for projects of similar length
and complexity. One inspector is assigned full-time to each of the HDD
sites and will assist in monitoring the progress of the drill. Excess
drilling fluids (non toxic bentonite clay and water) and cuttings produced
by the HDDs will be disposed of at an approved disposal site. Water,
to mix the drilling fluids and complete the pipe string hydrotests,
will be brought in from off site and stored in tanks at the entry and
exit locations.
|